Reduced the deficiencies to zero, while increasing the project throughput 2X
Implement the strategic Project Management
About the Client:
Flowers Foods, headquartered in Thomasville, GA, is a producer and marketer of packed bakery food. The company operates 47 bakeries producing bread, buns, rolls, snack cakes, pastries, and tortillas. Flower Foods’ products are sold regionally through a direct store delivery network that encompasses the East, South, Southwest, West, and the Northwest regions of the United States and are delivered nationwide to retailer’s warehouses.
Industry
Process Manufacturing, FMCG
The Project Challenges:
Our team was tasked to implement a process which can be used to plan, control and structure the development and implementation of information system or solution that is cost-efficient, effective, and high quality
The company wanted Visvero to help them with:
Ensure compliance with program controls impacting both SOX and non-SOX systems
Create accountability using RACI for SDLC artifacts and approval/sign-offs
Prove consistent collaboration & participation in the solution delivery process
Eliminate Information Systems/Solution production deficiencies associated with COBIT Program Development controls
Establish framework for building implementing and enhancing systems based on IA Framework, restricted data and compliance controls
React quickly to fulfill IT work request and build business community confidence on delivery date commitments
Reduce unnecessary overhead
Identify and mitigate problems associated with delivering information systems or solution
Visvero's Solutions Approach:
Implemented enterprise wide Project and Systems Delivery Methodology that uses risk-based eligibility criteria on IT Work request to determine SDLC process type.
Project Roadmap: Allows teams to locate where they are and what are the expected process steps.
Improved project quality:
Prescriptive guidance using templates, punch list and consolidated documents
IA Framework, IT Security, IT Compliance integrated into SDLC
Process Flexibility: No Longer one size fits all.
Lane Determination
Eligibility criteria
Stronger teams – Clarity around roles & responsibilities
Intake Management using SLA
Developed and Implemented Software Development Lifecycle (referred to as PSDM) with Governance and Project Monitoring / Control processes to include.
Prepared Process Diagrams that can be accessed from SharePoint and hyperlinked to each process type (Normal, Lite, Super-lite Project and Systems Delivery Methodology- PSDM)
Published Prescriptive process, procedures, templates that can be used for creating SDLC artifacts regardless of methodology approach (waterfall, iterative, agile).
Prepared RACI model- reflect roles and responsibilities associated with completing PSDM artifacts and approvals.
Developed and trained IT SLT, Technology Directors, IT personnel (employees, contractor, vendors)
Developed CBT training modules that can be used for onboarding new IT personnel
Developed checklist for stage gate reviews to improve quality and address risk impacting solution
Trained Flower’s IT department (IT-SLT, Directors, employees, contractors, vendors)
Overall Performance & Results:
No company deficiencies identified in last 2 quarters due to Program Development controls
Increased number of projects moved completed.
Baseline: 2018 had a total of 43 projects for periods Q3 & 4 No SDLC in place only a 1-page guide, 6+Significant deficiencies identify for Flowers
Year 1- 2019 = 14 projects completed in Q3/Q4 with no significant deficiencies identified in production. PSDM Ph 1, Intake/Initiate Phase implemented and trained
Year 2- 2020 = 20 projects completed in Q1/Q2 with no risk items identified by internal audited which need remediation.